PROJECT TITLE:
Extension of NPDC Network via Fibre Optic Cable to the venue for IGHF Commissioning
Date of Completion: 22nd December 2020
Scope of Work: Extension of NPDC network via fibre optic cable to the venue for Integrated Gas Handling Facility commissioning at Oredo Flowstation and Gas Loading Station include but not limited to the following;
- Construction of 45meters Telecommunication Mast, at least 3km away from the venue of the event
- Provision of a reliable power source such as solar and inverter at the base of the mast
- Provision of a power generator set for backup
- Provision of a Shelter/Container at the base of the Mast to House all the Active and Indoor devices
- Provision of a Shelter/Container at the event centre to House the Active Devices
- Provision of two Cisco Switches (WS-C3650-24FD-S) or (WS-C3650-48FD-S)
- Provision of two Cisco Routers (ISR4221/K9)
- Radio link between NPDC head office Benin City and the Mast at Oredo Gas Flow Station (150 mbps across), Frequency Band: 7 GHz or 15 GHz
- Laying of fibre optic cable between the Mast at the Base Station and event centre
- Proper termination of fibre and integration with all the active devices at both ends
- A roll of UTP cable (Cat6 outdoor cable), crimping tool and connector accessories
- Five long electrical extension boxes
- Configuration and integration with NPDC network
- Testing and Commissioning
- Decommissioning and site clearance after the project